Client: Stockland
Date: June 2018

Project Overview
Calleya Town Centre was a 500sqm Trafficable cobble stone pavement. LBP constructed the entire project from Concrete subgrade, Aco drain installation and drainage connection, All in-situ concrete Kerbing and supplying all materials to undertake the work. The Stone comprised 7 different types/colours (100x100x125mm) and were laid in a random percentage colour pattern. The mortar and grout system used was Steintec.